Cement bags and sand for any plastering job — by area, thickness and mix — with cost at your rates.
Plaster thickness drives everything: every extra 3 mm on a wall is 25% more cement and sand at 12 mm. Uneven brickwork, filled with plaster, quietly doubles consumption on some walls.
100 m² of internal wall at 12 mm in 1:6: wet 1.2 m³; dry 1.2 × 1.27 = 1.524 m³; +5% = 1.600 m³; cement 1.600 ÷ 7 = 0.229 m³ = 329 kg ≈ 6.6 bags (order 7); sand 1.37 m³ (48 cft).
Fix level dots and screeds first so the thickness is controlled, cure plaster for at least 7 days, and track cement per floor so an over-thick floor shows up early.
Contractors set a cement-per-square-metre target for each plaster type and compare it floor by floor with what the store issued.
Rebota's Daily Site Log records plaster area done and cement issued each day, and flags floors where consumption runs above the estimate.