Reconcile your actual stock movement against the BOQ — or let the calculator compute the theoretical requirement from your work done and concrete grade.
Cement wastage is the gap between the cement quantity your BOQ accounts for and the cement quantity actually consumed on site. Several distinct sources contribute: (1) pour-level over-batching from imprecise measurement — judgement-based batching adds 5–8% per pour; (2) storage spoilage from exposed bags absorbing moisture and lumping; (3) transfer loss from torn bags, spillage during mixing, and leftover mixed concrete dumped unlogged; (4) over-thick pours due to inadequate supervision and no live comparison against BOQ targets; (5) pilferage from unlocked or uncontrolled stores. These sources operate independently, which means sites with poor controls across multiple areas routinely exceed 8–10% wastage without any single pour looking alarming.
A contractor pouring 600 m³ of M20 concrete (theoretical requirement: 4,800 bags) and 2,000 m² of plastering (640 bags theoretical) has a total BOQ of 5,440 bags. Using volume batching and shared supervision, actual consumption of 5,980 bags represents 9.9% wastage — ₹2.07 lakh in excess cement at ₹380/bag landed cost. Switching to weight batching alone (IS 456) typically recovers 3–4 percentage points, saving ₹1.1–₹1.5 lakh on this single phase.
Top-performing sites run a daily material reconciliation: bags issued from store vs theoretical BOQ consumption for that day's pour, with a named engineer signing off the difference. Batching is by weight (weigh batcher for structural, calibrated farma for non-structural). Cement is stored covered with FIFO rotation and issued only against a signed challan. Damaged and pilferage losses are tracked in separate ledger lines — when pilferage is folded into "material overrun" it stays invisible and continues.
Top contractors assign a dedicated storekeeper who issues cement only against a signed pour challan, reconciles the store count daily against the issue register, and flags any discrepancy to the site engineer the same day. Batching uses a weigh batcher (for structural pours) or weekly-calibrated farma (for non-structural). The site engineer compares actual consumption against theoretical BOQ after every pour and requires a written explanation for any pour over 105% of theoretical.
Rebota's Daily Site Log captures cement issued per pour, automatically compares it against the BOQ quantity for that work item, and raises an AI alert the moment cumulative site wastage crosses your configured threshold — giving you a correctable window while pours are still ongoing, not a post-mortem after the slab has been cast.