Number of bricks, cement bags and sand for any brick wall — with openings deducted, wastage added and the total cost at your rates.
Bricks are bought by the thousand and broken by the hundred. Ordering on a rough "500 per cubic metre" for every brick size, or forgetting the openings, leads to either a half-truck of surplus or a stop while more arrives.
A 10 m × 3 m one-brick wall (230 mm) in standard bricks, no openings: volume 6.9 m³; bricks with 10 mm joints = 6.9 ÷ (0.24 × 0.125 × 0.085) = 2,706, plus 5% = 2,842. Wet mortar = 6.9 − 2,706 × 0.00198 = 1.53 m³; dry = 1.53 × 1.15 × 1.33 = 2.34 m³; 1:6 mix: cement 0.335 m³ = 482 kg ≈ 9.6 bags (order 10), sand 2.0 m³ (71 cft).
Measure the bricks actually delivered (ten in a row) — local bricks are often smaller than nominal, which changes the count per m³. Stack bricks close to the work to cut breakage.
Estimators take brickwork quantities from the BOQ wall by wall, deduct openings, and set a brick and mortar budget per floor that the site tracks against deliveries.
Rebota links brickwork BOQ items to material issued from the store, so bricks and cement used are compared with what the work should have consumed.