Earthwork volume for pits and trenches, the loose volume to carry away, the number of truck trips and the cost.
Earthwork is paid by the cubic metre and the truck trip, and both are easy to inflate: pits dug wider than needed, trips counted twice, or loose volume billed as in-situ volume.
A 2 × 2 m footing, 1.5 m deep, with 0.3 m working space and vertical sides: 2.6 × 2.6 × 1.5 = 10.14 m³. In ordinary soil (25% swell) that is 12.7 m³ loose — 3 trips in a 6 m³ tipper.
Measure excavation by levels before and after, pay on in-situ volume, and log every truck trip with the vehicle number and time.
Contractors take levels before and after excavation, agree the quantity with the client's engineer, and reconcile truck trips with the loose volume.
Rebota's Daily Site Log records excavation progress and equipment hours, and the equipment module compares fuel and trips with the work done.