Cement, sand, aggregate and water for any volume of nominal-mix concrete, in m³, cft and brass, with cost at your rates.
Concrete is mixed on site by the shovel and the bucket. A mix that is 10% rich wastes cement on every pour; a mix with extra water loses strength that no curing brings back. Knowing the exact quantities per batch keeps both in check.
1 m³ of M20 (1:1.5:3), no wastage: dry volume 1.54 m³; cement 1.54 ÷ 5.5 = 0.28 m³ = 403 kg = 8.06 bags; sand 0.42 m³ (14.8 cft); aggregate 0.84 m³ (29.7 cft); water at w/c 0.5 = 202 litres.
Batch with gauge boxes sized to one 50 kg bag, add water by measure, and cast cube samples for every pour. Use a design mix for M25 and above.
Sites with steady quality use a design mix, batch by weight, and track cement per cubic metre poured against the mix design so over-use is seen at once.
Rebota records each pour in the Daily Site Log with cement issued, and compares cement per m³ against the planned mix for every pour.